S-164 Batesville Road Phase II

Project Information

Description

  • SCDOT Pin number P030554
  • Widen to 3 lanes with curb, gutter, and sidewalks from Pelham Road to the Parkway

Purpose

  • Provide additional capacity to address existing and future traffic congestion while improving left turns at intersections

Need

  • Due to growth in the area, the corridor is experiencing large increases in traffic
  • Batesville Road distributes traffic from surrounding residential areas to SC 14 and Woodruff Road

Status

  • Due to the uncertainty of the I 85 widening project, this project is currently on hold. ROW has been shifted to FY 2028 with Construction following in FY 2029. Road Construction, Bridge Construction, Utility and CE&I Phases, and the let date were moved to FY 2030. When there is a clear path forward, funding will be adjusted accordingly.

 

Targets Impacted (Click here for further explanation)

 

Funding
Source
Funding
Amount
% Total
Guideshare $14,100,000 100%
Total $14,100,000 100%

 

Phase Funding
Amount
% Total
Preliminary Engineering $1,200,000 9%
Right-of-way $1,900,000 13%
Construction $11,000,000 78%

 