S-154 over Huff Creek Bridge Replacement

Project Information

SCDOT Project Page

Description

  • SCDOT Pin number P038260
  • Bridge replacement

Purpose

  • To maintain good infrastructure condition

Need

  • The bridge has been determined to be in need of replacement

Status

  • Construction has begun. The old bridge has been removed and construction is on schedule. Bents 2 and 3 are currently being constructed and beams are expected to be set in August. Estimated completion is December 2024.

 

Targets Impacted (Click here for further explanation)

 

Funding
Source
Funding
Amount
% Total
Non-Guideshare $5,450,000 100%
Total $5,450,000 100%

 

Phase Funding
Amount
% Total
Preliminary Engineering $1,000,000 18%
Right-of-way $125,000 2%
Construction $4,325,000 79%

 