S-164 Batesville Road Phase II

Project Information

Description

  • SCDOT Pin number P030554
  • Widen to 3 lanes with curb, gutter, and sidewalks from Pelham Road to the Parkway

Purpose

  • Provide additional capacity to address existing and future traffic congestion while improving left turns at intersections

Need

  • Due to growth in the area, the corridor is experiencing large increases in traffic
  • Batesville Road distributes traffic from surrounding residential areas to SC 14 and Woodruff Road

Status

  • Project is currently on hold

 

Targets Impacted (Click here for further explanation)

 

Funding
Source
Funding
Amount
% Total
Guideshare $14,100,000 100%
Total $14,100,000 100%

 

Phase Funding
Amount
% Total
Preliminary Engineering $1,200,000 9%
Right-of-way $1,900,000 13%
Construction $11,000,000 78%

 

Construction Photos

*There are no construction photos at this time.