Bridge S-4-75 at US-29

Project Information

Description

  • Bridge Replacement

Purpose

  • To maintain good infrastructure condition

Need

  • Bridge has been determined to be in need of replacement

Status

  • PE to restart for bridge rehab project
  • In Right-of-Way Acquisition
  • Estimated November 2021 letting

 

Targets Impacted (Click here for further explanation)

 

Funding
Source
Funding
Amount
% Total
Non-Guideshare $18,243,000 100%
Total $18,243,000 100%

 

Phase Funding
Amount
% Total
Preliminary Engineering $2,000,000 11%
Right-of-Way $1,243,000 7%
Construction $15,000,000 82%

 

Construction Photos

*There are no construction photos at this time.