GPATS.org

Home

About GPATS

Horizon2045

Interactive Maps

Projects

Plans
Programs
Traffic Counts Data
Social
 

 

Back to Projects List

Bridge S-4-75 at US-29

Project Information

Description

  • SCOT Pin number 0031268
  • Bridge Replacement

Purpose

  • To maintain good infrastructure condition

Need

  • Bridge has been determined to be in need of replacement

Status

  • Contractor currently working on constructing the new median on US 29, approach slabs for the overpass as well as the barrier wall along the bridge. Estimated completion date is 07/2024.

 

Targets Impacted (Click here for further explanation)

 

Funding
Source
Funding
Amount
% Total
Non-Guideshare $18,243,000 100%
Total $18,243,000 100%

 

Phase Funding
Amount
% Total
Preliminary Engineering $2,000,000 11%
Right-of-Way $1,243,000 7%
Construction $15,000,000 82%

 

Construction Photos

© Copyright 2020 Greenville-Pickens Area Transportation Study, All rights reserved.